LNG LIQUEFACTION PLANT


Project Estimates

Key Quantities

Nature

Liquefaction Plant - WBS

Nature

Project Cost Data

Nature

1


Project Schedules

Master Schedule

Nature

Project Timeline

Nature


2


Project Fragnets

Site Preparation

Nature

Tank and Marine

Nature


3


Project Reports

Select
Show more data
Select
Back

4


Project Subcontracts Status

Main Civil Works

5,845,055 Initial Contract Value


00 Addendum


5,845,055 Original Contract Amount


5,845,055 Amount Committed to Date


52,605 Changes total


5,950,000 Amount to Compromise




Show more data

Main Civil Works

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


5,950,000 Earned to Date


yy/mm/dd Date Completed



Back

Structural Steel

4,645,055 Initial Contract Value


00 Addendum


4,645,055 Original Contract Amount


4,645,055 Amount Committed to Date


52,605 Changes total


4,950,000 Amount to Compromise




Show more data

Structural Steel

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


4,950,000 Earned to Date


yy/mm/dd Date Completed



Back

Jetty Piping Insulation

3,745,055 Initial Contract Value


00 Addendum


3,745,055 Original Contract Amount


3,745,055 Amount Committed to Date


52,605 Changes total


3,950,000 Amount to Compromise




Show more data

Jetty Piping Insulation

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


3,950,000 Earned to Date


yy/mm/dd Date Completed



Back

5