LNG TERMINAL PROJECT


Project Estimates

Terminal Price Breakdown

Equipment Supply

Jetty Civil WBS

Jetty Steel WBS

Terminal WBS

1


Project Schedules

Nature

Nature


2


Project Reports

Nature

3


Project Subcontracts Status

BOG - Civil Works

5,845,055 Initial Contract Value


00 Addendum


5,845,055 Original Contract Amount


5,845,055 Amount Committed to Date


52,605 Changes total


5,950,000 Amount to Compromise




Show more data

BOG - Civil Works

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


5,950,000 Earned to Date


yy/mm/dd Date Completed



Back

Structural Steel - Booths

4,645,055 Initial Contract Value


00 Addendum


4,645,055 Original Contract Amount


4,645,055 Amount Committed to Date


52,605 Changes total


4,950,000 Amount to Compromise




Show more data

Structural Steel - Booths

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


4,950,000 Earned to Date


yy/mm/dd Date Completed



Back

Jetty Piping Insulation

3,745,055 Initial Contract Value


00 Addendum


3,745,055 Original Contract Amount


3,745,055 Amount Committed to Date


52,605 Changes total


3,950,000 Amount to Compromise




Show more data

Jetty Piping Insulation

99.6% Scheduled Percent Completion


99.6% Actual Percent Completion


yy/mm/dd Original Contract Completion Date


yy/mm/dd Extended Contract Completion Date


yy/mm/dd Estimated Completion Date


3,950,000 Earned to Date


yy/mm/dd Date Completed



Back

4