LNG TERMINAL PROJECT
Project Estimates
Terminal WBS
1
Project Schedules
2
Project Reports
3
Project Subcontracts Status
BOG - Civil Works
5,845,055 Initial Contract Value
00 Addendum
5,845,055 Original Contract Amount
5,845,055 Amount Committed to Date
52,605 Changes total
5,950,000 Amount to Compromise
BOG - Civil Works
99.6% Scheduled Percent Completion
99.6% Actual Percent Completion
yy/mm/dd Original Contract Completion Date
yy/mm/dd Extended Contract Completion Date
yy/mm/dd Estimated Completion Date
5,950,000 Earned to Date
yy/mm/dd Date Completed
Structural Steel - Booths
4,645,055 Initial Contract Value
00 Addendum
4,645,055 Original Contract Amount
4,645,055 Amount Committed to Date
52,605 Changes total
4,950,000 Amount to Compromise
Structural Steel - Booths
99.6% Scheduled Percent Completion
99.6% Actual Percent Completion
yy/mm/dd Original Contract Completion Date
yy/mm/dd Extended Contract Completion Date
yy/mm/dd Estimated Completion Date
4,950,000 Earned to Date
yy/mm/dd Date Completed
Jetty Piping Insulation
3,745,055 Initial Contract Value
00 Addendum
3,745,055 Original Contract Amount
3,745,055 Amount Committed to Date
52,605 Changes total
3,950,000 Amount to Compromise
Jetty Piping Insulation
99.6% Scheduled Percent Completion
99.6% Actual Percent Completion
yy/mm/dd Original Contract Completion Date
yy/mm/dd Extended Contract Completion Date
yy/mm/dd Estimated Completion Date
3,950,000 Earned to Date
yy/mm/dd Date Completed