Residential & Commercial: General Reports

Schedule Programmed

Nature

Sitework - Online Views

Project No. 121234
Project No. 121234
Project No. 121234

Expense Curve (S-Curve) - Programmed




Evolution of Material Prices


Nature

Equipment List

Equipment

BobCAT S175

Concrete pump

Concrete pump

Wacker Compactor

Compressor 250

Mobile crane (30 ton)

Torsion bar equipment

Bar cutting equipment

Forklift

Unidades



Material Project Inventory - ABC Analysis

Monthly CashFlow

Nature

Pictures


Pictures





Substructure - Work Progress Report

Construction Progress Report

Disciplines Progress Reports



Earned Value Report

Trade Status Report




Substructure - Contracts Status

Contracts List

Contract Details

CONCRETE WORKS

845,055 Initial Contract Value

00 Additions

845,055 Original Contract Amount

845,055 Current Committed Amount

52,605 Total Changes

950,000 Amount to Commit

Show more

CONCRETE WORKS

99.6% Programmed Completion Percentage

99.6% Actual Completion Rate

Back
Superstructure - Work Progress Report

Construction Progress Reports

Disciplines Progress Report



Earned Value Report

Trade Status Report




Superstructure - Contracts Status

Contracts List

Contract Details

CONCRETE WORKS

845,055 Initial Contract Value

00 Additions

845,055 Original Contract Amount

845,055 Current Committed Amount

52,605 Total Changes

950,000 Amount to Commitr

Show more

CONCRETE WORKS

99.6% Programmed Completion Percentage

99.6% Actual Completion Rate

Back
FINISHES - Work Progress Report

Construction Progress Reports

Disciplines Progress Reports



Earned Value Report

Trade Progress Report




FINISHES - Contracts Status

Contracts List

Contracts Details

MEP - Work Progress Report

Construction Progress Reports

Disciplines Progress Reports



Earned Value Report

Trade Progress Report




MEP - Contracts Status

Contracts List

Contracts Details